Pricing a kitchen installation properly

A kitchen install looks like joinery but prices like a small refurbishment: services moves, plastering, flooring, a stone worktop with its own timetable, and a client living out of a microwave who counts every idle day. The quotes that make money treat it that way from the start.

Scope first: fit-only or full install?

The single biggest source of kitchen pricing grief is two people holding two different definitions of the job. "Fitting a kitchen" can mean hanging units on finished walls in a ready room, or it can mean strip-out, rerouting services, plastering, flooring, fitting, worktops, tiling, appliances and decoration. The price difference is a factor of three or four, so nail the definition before a single number is written.

Walk the room with the client and agree in writing where your work starts and ends: who supplies the kitchen, who takes delivery and checks it, whether the floor goes under the units or up to them, who fits and who commissions each appliance, and what happens to the old kitchen. Ten minutes of boundary-drawing here replaces a month of "I assumed you were doing that". The mechanics of recording it are in exclusions and assumptions.

The services layer: where the real money hides

New layouts almost never sit on old services. The sink crosses the room, the hob goes from gas to induction, the island wants power and waste in the middle of the floor. Each move is a real piece of first fix work with making-good behind it:

Price each move as its own line with its making-good (chases plastered, floors patched). This layer routinely accounts for a quarter to a third of a full install, and it is the layer lump-sum quotes swallow whole.

Every arrow is a priced line, not a footnote Old sink New sink Hot, cold and waste rerouted: 4 m Gas hob Island: induction + power + waste New circuit + gas capped Extract duct Three moves on this plan = first fix, floor lifting, chasing, certification and making good.
A plan-view of typical services moves. Each dashed arrow carries labour, materials, certification and making-good.

The worktop gap: the week that wrecks programmes

Stone and solid-surface worktops cannot be templated until the base units are fitted, level and fixed, and fabrication then takes several working days, commonly a week or more. That gap is a fact of the material, not a failure, but it must be in both the programme and the price: a return visit for the fitters, a temporary worktop if the client needs a working sink (a spare length of laminate earns its keep here), and the plumber back for final connection after the stone lands.

Quote the gap explicitly. "Units fitted week one; worktops templated day eight, fitted around day fifteen; final plumbing and tiling follow" reads like a builder who has done this before. Silence reads like a fortnight of mystery, and mid-job silence is where client relationships go to die.

The worktop gap: plan it or be surprised by it Strip + first fix Units fitted Template + fabricate 5 to 10 working days Stone fitted Finish Week 1 The gap: no trades on site Week 3 Price into the gap: a return visit for fitters, a temporary worktop and sink, the plumber's final connection, and a client told the plan in advance.
Stone worktops impose a mid-job pause. The quote and the payment schedule should both know about it.
Programme note: the worktop gap is also a payment-schedule point. Do not let a big stage payment hang on "kitchen complete" when a stone lead time you do not control sits in the middle of it. Split the stage either side of the gap, as covered in stage payments that protect your cash flow.

Units, worktops and appliances: who supplies what

ElementUsual arrangementPricing treatment
Units and doorsClient buys, or PC sum through youPC sum for supply; fitting labour firm, per unit count
Worktops, laminateSupplied with kitchenFitting firm: cuts, joints, edging per length
Worktops, stone or solid surfaceSpecialist supply and fitNamed subcontract sum plus your attendance and the programme gap
AppliancesClient buysFit and connect each, priced per appliance; commissioning per maker's terms
Sink, taps, brasswareClient buys or PC sumPC sum for supply; connection labour firm

Count the units off the plan and price fitting per cabinet with an uplift for corners, larders, integrated appliance housings and anything handleless. Wall-unit runs on out-of-plumb walls of old houses eat hours; if the survey shows walls a spirit level laughs at, say so and price the scribing honestly.

The lines that go missing

Beyond the services and the worktop gap, the classic misses on kitchen quotes: strip-out and disposal of the old kitchen, protection of adjacent rooms and floors, plastering after the chases (walls and often the ceiling once the old wall units come off), flooring under or around units and the threshold detail, tiling or splashback with trims, plinth ventilation for integrated appliances, cornice and pelmet fitting, mastic throughout, and a return-visit allowance for the snags that surface once the client starts using the room. None of these is large. Together they are commonly 10 to 15 percent of the job, which for most firms is the entire margin. This is the same disease we diagnosed in estimating mistakes that kill margin: the price was not wrong, it was incomplete.

The reliable cure is to price from a full bill of quantities rather than from memory. QS Quoter builds a draft from a description of the install or the kitchen plan, at your own rates, with services moves, making-good and sundries on their own editable lines, plus a client copy and a private copy showing every rate. The review remains yours, and the structure makes possible omissions visible.